INFRASTRUCTURE

Misurata Infrastructure Works


Misurata Free Zone Infrastructure Works

Client : Misurata Free Zone Administration

Consultant : MVV-Decon

Start Date : October 2009

Key features of Work Scope:
The project located in Misurata -Libya consists of construction of infrastructure works and covers an area of 350 hectares.
Within the scope of the works the following works will be executed.

   · Water supply network

Water supply network consists of approximately 21 km pipe lines by use of HDPE pipes ranging from 25 mm to 250 mm in diameters  for potable, fire fighting and irrigation systems.

On the system there are one concrete water storage of 3500 cubic meter capacity with one pumping station and relevant mechanical and electrical works.

    · Storm water network

Storm water system consists of construction of 20.5 km pipeline, 9.6 km gully connections, 366 manholes, one pump station including electrical and mechanical works and 1 km sea discharge line of HDPE type pipe.

Type of the pipes to be used for the system is uPVC and diameters vary between 300-700 mm.

    · Sewer network

Sewer system consists of 18.5 km pipeline uPVC pipeline with diameters ranging between 200 mm – 700 mm, 388 manholes, 3 lifting stations, one pump station with electro-mechanical works and 3 km mains to sewage treatment plant.

    · Road works

Road works includes 24 km asphalt roads with all related curbstone, signage and marking works.

Total asphalt area is 385.000 square meters.

Landscaping, construction of 85.000 sqm walkways are also included within scope of road works.

    · Electrical and communication networks

Electrical and communication network consist of construction of cable canals of different cross sections by use of corrugated PE type pipes and includes related manholes.

Length of communication and electrical networks are 214 km in total.