ACG Topside Fab. Yards - 2
ACG FFD Project, Phase 2 Topside Fabrication Yards
Client : AIOC-BP
Main Contractor : J. Ray McDermott
Key Designer : Kellogg Brown & Root
Consultant : Kellog Brown & Root
Start Date : February 2002
Finish Date : February 2004
Key features of Work Scope
The project consisted of the upgrading and refurbishing of SPS (Subsea Production System Platform) fabrication yard.
TML-Borova’s scope of work mainly comprised;
· Construction of new skid-ways, jacking points, casting of skid-way blocks. Earthquake load supports, pile support load-in concrete slab, upgrade rail track,
· Refurbishing the assembly area / Quay wall;
· Increasing loading capacity of quay wall including bored in situ piles;
· Clear area for all scrub, debris, and the like;
· Major Heavy Civil Work Items:
· Miscellaneous Civil site works;
· Mechanical works;
· Electrical works;