Foça WWTP& Sea Outfall
Foca Wastewater Treatment Plant and Sea Outfall Facilities
Client : Municipality of Foça, Izmir, Turkey
Main Contractor . TML-Çevtas JV - Pridesa Consortium
Key Designer : TML-Çevtas JV - Pridesa Consortium
Consultant : Tugal-Tistaş JV
Start Date : January 2002
Finish Date : January 2004
Key features of Work Scope:
Treatment Plant was designed for a flow of 14.083 m³/day
Sea Outfall was designed as 3300m with Ø 500 mm HDPE Pipe including 110m diffusers.
The Project was the construction and operation of Wastewater treatment Plant with a 3410 m long 500 mm diameter Sea Outfall Facilities of Foça city.
Scope of work included;
· Construction of process structures for treatment plant,
· Construction of supporting structures, all process pipelines,
· Excavation and filling works for the above works,
· Surface finishes,
· Supply and installation of all mechanical and electrical works of the treatment plant,
· Civil, mechanical and electrical works,
· Modification of five pump stations,
· Operation of the treatment plant for a year.